October 2024

The header announces an "October 2024 Bond Construction Early Package Update" for Castleberry ISD, featuring the 2024 May Bond initiative with the motto "Inspire. Empower. Innovate."
This photo shows the site of a removed breezeway between two buildings on the Castleberry ISD campus. The area is now cleared of the structure, with visible earthwork and soil where the breezeway once stood. The image captures a transition space with open sky, trees in the background, and remaining building structures on either side, indicating ongoing construction and site preparations as part of the district's bond project updates.This photo displays a temporary ADA-accessible bridge constructed on the Castleberry ISD campus. The bridge, made of metal scaffolding with guardrails, provides a safe and accessible pathway over uneven terrain during ongoing construction. Positioned near a building and beside a fenced-off area, this structure ensures accessibility compliance and convenience for individuals with mobility needs as part of the district’s bond-funded construction updates.








The image shows the exterior of the CHS building with a newly constructed hallway area leading to the basement. A concrete ramp with metal railings provides accessibility, ensuring easy access to the basement level. This addition enhances connectivity and accessibility for the CHS basement, with a clean, modern look that complements the building's structure.
The image shows a cleared, dirt-covered area where tennis courts once stood, indicating that demolition has recently taken place. The site is open with a grassy perimeter, bordered by trees in the background under a clear blue sky. This image represents the initial phase of demolition and preparation for future development on the former tennis courts.
The images show the area near the library stairwell where an elevator has been removed, replaced temporarily with a lift to maintain accessibility. The left image highlights the stairwell, while the right image provides a close-up view of the temporary lift mechanism. This setup ensures that individuals can continue to access different building levels during the renovation or replacement of the original elevator.   












Early Construction Project Cost Estimate: $1,478,359.00
Early Package Project Paid to Date: $692,743.00